[sha2017-orga] Datacenter Migration BIT -> DCG
Matthew Frost
m.frost at mattronix.nl
Sun Aug 20 15:55:35 CEST 2017
Attention all,
On the 29th of August will be migrating all services besides tickets from Datacenter BIT to Datacenter DCG in Amsterdam.
This is to be compliant with the agreement of moving our equipment out of BIT before the end of the month.
Expect a downtime from 10AM till maximum 14:00PM as we move / renumber and get the services required by the teams online all services that are no longer required will be shut down on the 27th.
—
Kind Regards, Matthew Frost
SHA2017 Sysadmin Team Lead - https://sha2017.org <https://sha2017.org/>
Board Member Techinc Amsterdam - https://techinc.nl <https://techinc.nl/>
IHTG (Inter Hackerspace Technical Group) Member
weho.st <http://weho.st/> member - https://weho.st <https://weho.st/>
Technical Solution Consultant - Proact Netherlands B.V.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.sha2017.org/cgi-bin/mailman/private/orga/attachments/20170820/497d0ef8/attachment.html>
More information about the Orga
mailing list