[sha2017-orga] Power needs
Ralph Willekes
benadski at gmail.com
Fri Jul 7 15:15:28 CEST 2017
Hi,
>From some teams we already have had some details about power usage, thanks
for that!
We'd like to know from other teams that use much (= above 400V/32A) power
what they need.
(This also applies if you must have more than a dozen or so of Schuko
sockets available.
But consider getting a 1.5mm2 or bigger wired "stekkerdozen" yourself as it
is cheaper!)
Power on the orga field will be ample, but if you need more than 32A/400V,
please specify.
For the stages, we only have heard there are two LED screens there (Pa&No),
nothing more.
How much more power do you need for lighting, audio, etc.? Isn't there a
screen in "Re"?
We still have zero info about the food court too. We'd like to know the
number of vendors f.i.
There will be a 3x63A (44kVA) line there with many 32A 5pol CEE sockets
available within
a few meters. There's also many Schuko sockets there.
*Please note, there are no 16A 5pol. CEE sockets anywhere, use 32A. 16A
blue, same.*
*We have very few 230V Schuko to blue CEE 16A conversion cables, just use
Schuko!*
Best regards,
Ralph Willekes (benadski)
Team:Power
power at lists.sha2017.org
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.sha2017.org/cgi-bin/mailman/private/orga/attachments/20170707/04456ab9/attachment.html>
More information about the Orga
mailing list