[why2025-orga] Warehouse planning back to normal (Was: Early buildup delayed by 2 days? (Was: Request: ...))
Juerd Waalboer
juerd at tnx.nl
Sun Jul 13 19:19:33 CEST 2025
Boekenwuurm via Orga skribis 2025-07-13 18:31 (+0200):
>I double-checked it, and this week, it was made confirmed that the
>warehouse portacabin will be delivered early on the 31th.
That is good news, thanks for double-checking.
This means that if everything goes according to plan, the Warehouse will be available for other teams the morning of the Friday (-6), the first day of the "early buildup" phase.
Our build-up planning is as follows:
* Wednesday (-8): first people from Warehouse on site
* Thursday (-7) morning: delivery of portacabins, set up (temporary?) power
* Thursday (-7) afternoon: delivery of danish trolleys
* Thursday (-7) evening: delivery of goods from staging location (RevSpace)
* Thursday (-7) night: warehouse setup
* Friday (-6) morning: warehouse available
>For tear-down, it is currently planned to be picked up the Saturday of
>the tear-down, the day that it should be finished.
>This should be able to keep the original planning.
Saturday is fine with us. Last we heard about this was that Boels doesn't work in weekends and it would thus be postponed until Monday (like at SHA). Either is good, since after Friday the portacabins should be empty.
Our tear-down planning is probably:
* Thursday (7) noon: all team-storage gone
* Friday (8) morning: pickup of danish trolleys
* Friday (8) afternoon/evening: bakwagen leaves, warehouse empty
* Saturday (9): pickup of portacabins
Thanks,
Juerd
Team:Warehouse