[Logistics-leads] [why2025-orga] Boels order status

CH23 chaostwentythree at gmail.com
Fri Jul 4 22:46:04 CEST 2025


follow up: where I said "We need to be up and running before even
Heaven is put down", it should be "We need to be up and running before
even Heaven is getting furnished"

Thanks again!

On Fri, 4 Jul 2025 at 22:35, CH23 <chaostwentythree at gmail.com> wrote:
>
> Hi Manduca,
>
> As we discussed previously, we would need to have the portacabins by
> latest on the morning of the 31st, or during the 30th if that's not
> possible. For pickup, they can't be picked up before the end of
> saturday the 16th. Please make sure this will be arranged. We need to
> be up and running before even Heaven is put down, as we will be the
> main source for all tools and other buildup needs.
>
> Thank you!
>
> With kind regards,
> CH23 / Jochem
>
> On Fri, 4 Jul 2025 at 14:06, Manduca via Orga <orga at lists.why2025.org> wrote:
> >
> > Hi all,
> > The final boels quote has been processed. All requests and changes (that where send in before the deadline!) have been confirmed (except for 2 small mistakes, but they will be corrected) and are reflected in the boels spreadsheet.
> > Please do check the boels google spreadsheet for your team (link on request if you don't have it).
> > ATTENTION!
> > As there are no deliveries in the weekend, and we can not recieve everything on August 1st we will assume that delivery on August 4th is not a problem. If you need something earlier let us know exactly what, when and why. Then we can prioritze deliveries.
> > Mail this to logistics-leads at lists.why2025.org.
> > Regards,
> > Manduca
> > _______________________________________________
> > Orga mailing list
> > Orga at lists.why2025.org
> > https://lists.why2025.org/mailman/listinfo/orga


More information about the Logistics-leads mailing list